Building and Civil Engineering

contracting-harestanes

Client: Scottish Power
Main Contractor: Farrans (Construction) Ltd
More Info
The main project was to construct, commission and test a windfarm comprising 68 Wind Turbine Generators (WTGs) for the purpose of generating an output of up to 142MW to be exported to the national electricity grid network.

Our involvement was to surface the upgraded existing site access from the A701. This included the surfacing of 1,700m2 of access road with base, binder and HRA 55/14 surface course together with the associated tie-in with the A701.

There was an added complication in that we were required to maintain access to the site throughout the course of our works. This was overcome by undertaking the works at the weekend and utilising up to 30nr tippers per day to guarantee the supply of material from our plant at Troon.


contracting-gourock

Client: Caledonian Maritime Assets Ltd
Main Contractor: George Leslie Ltd
More Info
George Leslie Ltd was appointed as the Main Contractor for the new berth steps structure works at the Caledonian Maritime Assets Ltd Gourock Ferry Terminal.

The improvements were to be made in order to accommodate vehicle traffic when ferry services are transferred from Wemyss Bay to Gourock and to accommodate the passenger-only services currently operating from other berths at the terminal.

Hillhouse Contracts were contracted to undertake the shoreside works which included the planing and resurfacing of the car park and vehicle access routes to and from the terminal.

This included the planing and resurfacing of approximately 6,000m2 of carriageway. All planings were returned to our Glasgow Asphalt Plant at Cambuslang for recycling. The surfacing works required 700t’s of HRA 55/14 and were completed in one week.


contracting-decathlon

Client: Decathlon Sports
Main Contractor: Foreshaw Demolition
More Info
Hillhouse Contracts undertook the surfacing at the new Decathlon Sports Warehouse on Old Govan Road, Glasgow.

The surfacing works included:

  • 2,000m2 of pedestrian areas / footpaths
  • 4,500m2 of Hot Rolled Asphalt access roads and car park aisles
  • 600m2 of Stone Mastic Asphalt surface course
  • 2,000m2 of Multi Use Games Area laid with open graded binder and surface courses.

The works were successfully completed on time and within budget.