Local Authorities

barksimming

Client: East Ayrshire Council
Main Contractor: Hillhouse Contracts

More Info

This project was undertaken as part of the Ayrshire Roads Minor Works (2G) Framework which runs from October 2014 to September 2016 with the option to extend for a further 2 years.

The surfacing works included:

  • Cold Milling
  • Bond Coat
  • Regulating
  • 6,200m2 of carriageway surfacing (HRA and AC10 Enriched)

Our Volvo ABG 6870C paver was fitted with extension boxes to allow the AC10 Enriched to be laid in a single pass of the paver thereby eliminating the centre joint.


Client: East Ayrshire Council
Main Contractor: Hillhouse Contracts
More Info
This project was undertaken as part of the Ayrshire Roads Minor Works (2G) Framework which runs from October 2014 to September 2016 with the option to extend for a further 2 years.

The surfacing works included:

  • Installation and maintenance of the approved Traffic Management
  • 6,000m2 of Cold Milling
  • 6,000m2 of Bond Coat
  • 250t of Regulating (AC6)
  • 6,000m2 of carriageway surfacing (HRA 55/10)

Our Volvo ABG 6870C paver was fitted with extension boxes to allow the regulating and surface course to be laid in a single pass of the paver thereby eliminating the centre joint.


contracting-B7046

Client: East Ayrshire Council
Main Contractor: Hillhouse Contracts
More Info
This project was undertaken as part of the Ayrshire Roads Minor Works (2G) Framework which runs from October 2014 to September 2016 with the option to extend for a further 2 years.

The surfacing works included:

  • Installation, maintenance and removal of the approved Traffic Management
  • 5,100m2 of Cold Milling
  • 23,800m2 Bond Coat
  • 360t of AC6 Regulating
  • 4,500m2 of carriageway surfacing (HRA 55/10) and 7,400m2 of carriageway surfacing (AC10 Enriched)
  • Road Markings

The works were carried out at three locations on the B7046 between New Cumnock and Sinclairston in East Ayrshire.

Hillhouse Group

Hillhouse Group